Thank you for joining me for a public meeting on January 28th,, to discuss the Construction Management Plan for 1996-2000 and 2010-12 Bathurst St.

Please click here to review a copy of the presentation and draft construction schedule. Always feel very welcome to contact my office at councillor_matlow@toronto.ca should you have any further questions.

Unfortunately, the WebEx system that the City uses for public meetings crashed and the recording did not take. We deeply apologize for any inconvenience that this may cause. If you have any specific questions, my staff are more than happy to share any information or chat with you over the phone to clarify any questions you may have. Aside from the presentation by the two developer’s that is already posted on here, these are topics that had been discussed in the Q&A portion of the meeting:

  • Coordination between the various sites and Metrolinx and ensuring truck traffic is tightly controlled and monitored
  • Whether there are any anticipated utility disruptions to the community – none are anticipated
  • Ensuring access for emergency services via the laneway going north-south and accesses to all the businesses and residential properties that use that laneway as access points
  • Questions about continued closure of Peveril Hill N – no specific answers at the time of the meeting, as Metrolinx/Crosslinx controls the area still

I have recently heard back from the developer that will be redeveloping the current site at 875 Eglinton/2020 Bathurst, where the future LRT station entrance will be. They anticipate that their construction work will start later this summer,  but the impacts from their work will be relatively minor on the area south of the site, as they are planning to take over the existing Metrolinx working zone. This would mean that for Peveril, there would be no practical change as the trucks entering that site would be using Eglinton Avenue exclusively. Metrolinx is actually already conducting the demolition on their site as we speak, as the LRT station will be directly connected to this building. Once that is completed, we are expecting the developer to take over the site.

Please see these timelines that we have received from the three sites:

 

1998-2000 Bathurst Street:

Mar 2021 – Jan 2022: Demolition & shoring

Nov 2021 – Jul 2022: main building construction

Apr 2022 – Nov 2022: interior finishes

  • City’s Application Information Centre featuring more detail on the site at this link
  • City Planner on file: Sipo Maphangoh (Maphangoh@toronto.ca; 416-338-2478)

 

2010-2016 Bathurst Street:

Aug 2021 – Mar 2022: Demolition and shoring

Feb 2022 – Apr 2023: building construction

Oct 2022 – Dec 2023: internal building construction

  • City’s Application Information Centre featuring more detail on the site at this link
  • City Council approval from October 2019 at this link
  • City Planner on File: Jason Tsang (Tsang@toronto.ca; 416-392-4237)

 

875 Eglinton Ave W (2020 Bathurst Street):

Mar 2021 – May 2021: Demolition & shoring conducted by Metrolinx/Crosslinx

May/June 2021: Developer takes over site

June 2021 start for approx. 15 months: above grade construction of the building

2023: internal building construction & occupancy around Q4 2023

  • City’s Application Information Centre featuring more detail on the site at this link
  • City Council direction for the appeal of the site at this link
  • LPAT appeal settlement decision at this link
  • City Planner on File: Jason Tsang (Tsang@toronto.ca; 416-392-4237)

 

 